40 men can complete a piece of work in 15 days. 20 more men join them after 5 days they start doing work. How many days will be required by them to finish the remaining work? [ESIC-UDC, Exam 2016]
(a)$7\frac{2}{3}$ days
(b)$6\frac{1}{5}$ days
(c)$8\frac{1}{4}$ days
(d)$6\frac{2}{3}$ days
Answer
Answer (as printed): D