Subject: General Aptitude · Chapter: Time and Work · Exam: · Marks: · Difficulty:
40 men can complete a piece of work in 15 days. 20 more men join them after 5 days they start doing work. How many days will be required by them to finish the remaining work? [ESIC-UDC, Exam 2016]