A can complete a certain work in 4 minutes, B in 5 minutes, C in 6 minutes, D in 10 minutes and E in 12… · ABC26GN3417

Subject: General Aptitude · Chapter: Time and Work · Exam: P.C.S. 2009

A can complete a certain work in 4 minutes, $B$ in 5 minutes, $C$ in 6 minutes, $D$ in 10 minutes and $E$ in 12 minutes. The average number of units of work completed by them per minute will be
(a)0.16
(b)0.40
(c)0.80
(d)None of these
Answer
No answer key was printed for this question.
Explanation
No explanation was printed for this question.