A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in :
(a)$9 \frac{1}{5}$ days
(b)$9 \frac{2}{5}$ days
(c)$9 \frac{3}{5}$ days
(d)10 days
Answer
Answer (as printed):
Explanation
No explanation was printed for this question.