ABC26GN3490 · Time and Work

Subject: General Aptitude · Chapter: Time and Work · Exam: 2007 · Marks: · Difficulty:

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is
(a)$6 \frac{3}{5}$
(b)$8 \frac{1}{2}$
(c)$10 \frac{1}{5}$
(d)$13 \frac{1}{2}$
Answer
Answer (as printed): C
Explanation
B’s 3 days’ work =  × 3  = .  21  7  1 6 Remaining work =  1 −  = .  7 7 549  1 1 5 (A + B)’s 1 day’s work =  +  = .  14 21 42 5 Now, work is done by A and B in 1 day. 42 6  42 6  36 ∴ work is done by A and B in  × = days. 7  5 7  5  36  1 Hence, total time taken =  3 +  days = 10 days.  5 5  1 1 1  13